Contractual Penalty
“If they breach the contract, we’ll put in a penalty of CZK 500,000. That should make them careful.”
At first sight, that sounds logical.
But a contractual penalty is not a magic number that automatically makes a contract safer.
What exactly triggers the penalty?
Every individual breach?
Every day of delay?
Once for the entire breach?
From the first day?
Should the creditor still be entitled to claim damages in addition to the penalty?
What if the breach continues for a year and the penalty grows to several times the value of the entire contract?
And most importantly:
Can you clearly identify from the agreement which specific obligation the contractual penalty is intended to secure?
Under Czech law, parties may agree that a contractual penalty becomes payable if a particular contractual obligation is breached. The penalty may be fixed as a specific amount or determined according to an agreed calculation mechanism. The creditor does not need to prove that actual damage occurred in order to claim it.
That makes the contractual penalty a very useful contractual tool.
But precisely for that reason, it needs to be drafted carefully.
A contractual penalty should not punish everything you dislike about the other party’s behaviour. It should define in advance the financial consequence of breaching a specific contractual obligation.
SHORT ANSWER TO THE MAIN QUESTION
Under Czech law, a contractual penalty is a mechanism used to reinforce the performance of an obligation.
The parties agree in advance that if one party breaches a specified contractual duty, the other party becomes entitled to a contractual penalty in a fixed amount or calculated according to an agreed formula.
The creditor does not need to prove actual damage in order to claim the penalty.
The penalty may be included directly in the main agreement as a contractual penalty clause, or it may be agreed separately in a Contractual Penalty Agreement connected to an existing obligation.
The important issue is not whether the clause is called “Contractual Penalty”, “Penalty Provision” or simply included under “Sanctions”.
What matters is whether the secured obligation, the triggering breach and the method of calculating the penalty are sufficiently clear.
YOU MAY BE THINKING…
“How high can a contractual penalty be?”
“Does it have to be proportionate when the agreement is signed?”
“Can a court reduce it?”
“Do I have to prove that I suffered damage?”
“Can I claim both the contractual penalty and damages?”
“If the debtor pays the penalty, do they still have to perform the original obligation?”
“Can we agree on 0.1% for every day of delay?”
“Can there be a penalty for each individual breach?”
“And can we secure every single obligation in the agreement with a penalty?”
That last question is often where poor drafting begins.
A contractual penalty works well when it protects a specific important interest. Not when it is mechanically attached to every paragraph in the contract.
THE REAL PROBLEM IN PRACTICE: THEORY VS REALITY
In theory, the mechanism is simple.
The obligation says:
“The contractor shall deliver the work no later than 30 June.”
The penalty clause says:
“For every day of delay, the contractor shall pay CZK 5,000.”
The contractor is ten days late.
The penalty is CZK 50,000.
Simple.
Real contracts are rarely that clean.
For example:
“For breach of any obligation under this Agreement, the contractor shall pay a contractual penalty of CZK 100,000.”
For late delivery?
For one mistake in a report?
For failing to return an access card?
For disclosing critical trade secrets?
For each breach?
Or only once?
What if a single event breaches several contractual provisions at the same time?
The less precise the connection between obligation – breach – penalty amount, the more room there is for dispute.
Another common assumption is:
“If we make the penalty high enough, the court has to enforce it because the other party signed the contract.”
That is not a safe assumption either.
Under Czech law, a court may, at the debtor’s request, reduce a contractual penalty that is disproportionately high.
Modern Czech case law also emphasises that the court does not merely examine the abstract number written in the agreement. It considers the proportionality of the specific claim that has actually arisen, taking into account the circumstances of the breach and the legitimate interest the contractual penalty was intended to protect.
A contractual penalty should therefore not be designed around the question “what is the highest number the other side will sign?”. It should be designed around the actual risk it is meant to address.
BIGGEST RISKS AND COMMON MISTAKES
The same problems repeatedly appear in contractual penalty provisions:
- the secured obligation is not clearly identified,
- the penalty is linked to a vague duty such as “proper cooperation”,
- it is unclear what constitutes a breach,
- it is unclear whether the penalty is one-off or recurring,
- it is unclear whether it accrues per day, per week or per individual breach,
- the starting point for accrual is not defined,
- a percentage penalty has no clear calculation base,
- no maximum cap is set where one would make commercial sense,
- several penalties may accumulate uncontrollably,
- one event may trigger multiple penalty claims,
- the amount does not reflect the importance of the secured obligation,
- a daily penalty may become extreme if the breach lasts for a long time,
- the agreement does not address the relationship between the contractual penalty and damages,
- the parties automatically assume that both can always be claimed together,
- the due date is unclear,
- the mechanism for making the claim is not addressed,
- the penalty is confused with default interest,
- the penalty is used instead of properly defining the underlying obligation.
Another typical clause?
“For breach of this Agreement, the breaching party shall pay a contractual penalty of CZK 500,000.”
For what breach?
Any breach?
Even a minor administrative one?
Once in total?
For every occurrence?
A clause like this may create more uncertainty than protection.
First define the obligation. Then define the breach. Only then put a price on that breach.
HOW TO APPROACH IT: REALITY, NOT THEORY
With a contractual penalty, I would not start with the amount.
I would start with this question:
Which breach of this agreement would be important enough that I want a predetermined financial consequence without having to prove actual damage?
1. Select the obligations that genuinely matter
For example:
- deadline for delivery of work,
- deadline for vacating premises,
- confidentiality obligations,
- restrictions on the use of know-how,
- obligation to return documentation,
- obligation to remedy defects,
- obligation to provide specific cooperation,
- restriction on unauthorised solicitation of a particular customer,
- obligation to provide documents within a specified deadline.
Not every contractual duty needs a contractual penalty.
2. Define when the obligation is breached
With a deadline, this is usually simple.
With other duties, much less so.
For example:
“The contractor shall provide sufficient cooperation to the customer.”
What does sufficient mean?
If you attach a CZK 50,000 penalty to that wording, you may simply create a dispute about whether a breach occurred at all.
A contractual penalty is only as precise as the obligation to which it is linked.
3. Choose the calculation mechanism
The penalty may be:
one-off
CZK 50,000 for breach of confidentiality,
per occurrence
CZK 5,000 for each unauthorised use,
time-based
CZK 2,000 for each day of delay,
percentage-based
0.05% of a precisely defined amount for each day of delay.
Different mechanisms are suitable for different types of risk.
4. Think about accumulation
What if the contractor:
fails to deliver the work on time,
also fails to provide the documentation,
and also fails to hand over access credentials?
Do three separate penalties arise?
And if the failure to provide documentation lasts for 30 days, is there one penalty or 30?
This should not be decided for the first time when a lawyer is preparing a pre-action demand letter.
5. Consider a cap
Not every contractual penalty needs a maximum limit.
But for daily or percentage penalties, it is worth asking:
What happens if the breach continues for six months or two years?
A penalty that looked reasonable during the first month may eventually reach an amount that nobody seriously contemplated when signing the agreement.
6. Address the relationship with damages
This is one of the most commonly overlooked issues.
Under the default Czech-law rule, where a contractual penalty has been agreed, the creditor is not entitled to compensation for damage caused by breach of the same obligation covered by that contractual penalty.
This default rule can be modified by agreement.
That means a clause such as:
“For breach of confidentiality, the breaching party shall pay CZK 50,000.”
may not have the legal effect the creditor expects if they also assume that, in the event of CZK 1 million in damage, they will automatically receive both the penalty and the full damages claim.
The contract should consciously determine whether the contractual penalty:
- replaces damages on a lump-sum basis,
- applies in addition to damages,
- or interacts with damages in another agreed way.
7. Remember that payment of the penalty does not normally replace performance
Under Czech law, payment of a contractual penalty does not generally release the debtor from the original obligation.
If someone pays a penalty for delay in handing over documentation, that does not automatically mean:
“I paid the penalty, so I no longer have to provide the documents.”
This is particularly important where the creditor still needs actual performance.
PRACTICAL EXAMPLES
👉 A daily penalty that starts living a life of its own
A contractor agrees to pay CZK 10,000 for each day of delay.
When the agreement is signed, both parties expect that any delay would last only a few days.
The project later turns into a serious dispute.
The delay lasts 200 days.
The contractual penalty reaches CZK 2,000,000.
Only then do the parties start asking:
How important was the secured obligation?
What caused the delay?
What legitimate interest was the penalty intended to protect?
What consequences did the breach actually have?
Modern Czech case law on judicial reduction of contractual penalties places strong emphasis on the specific circumstances and consequences of the breach rather than merely comparing percentages or numbers mechanically.
A daily rate is therefore not just a small number. It is a mathematical mechanism whose long-term result should be tested before the agreement is signed.
👉 Contractual penalty for confidentiality breach
The agreement says:
“For breach of the confidentiality obligation, the contractual penalty is CZK 100,000.”
An employee of the contractual partner sends one email to five recipients.
Is that one breach?
Five breaches?
And what if the email contains confidential information from ten separate documents?
The wording “for each individual breach” may look precise, but without further definition it may still leave open what actually counts as one breach.
👉 CZK 50,000 penalty, CZK 3 million loss
A contractor breaches an important contractual duty.
The contractual penalty is CZK 50,000.
The customer suffers proven damage of CZK 3,000,000.
The customer assumes:
“I’ll take the contractual penalty and claim damages separately.”
But the agreement says nothing about the relationship between the contractual penalty and damages.
The default Czech-law rule may significantly change that expectation.
A contractual penalty is not only about the amount of the sanction. It is also about what agreeing the penalty does to other legal claims.
WHY YOU SHOULD BE CAREFUL WITH “I’LL DO IT MYSELF”
A contractual penalty clause looks extremely simple.
You might think it is enough to write:
“For breach of the obligation, the breaching party shall pay a contractual penalty of CZK 100,000.”
But a generic template does not know:
- which obligation is genuinely critical for you,
- what precisely constitutes breach,
- whether a one-off or continuing penalty is more appropriate,
- how long the penalty may continue to accrue,
- what amount a percentage penalty should be calculated from,
- whether individual penalties should accumulate,
- whether a cap is needed,
- whether the possible actual damage may be much higher,
- whether the right to claim damages should remain,
- whether actual performance is still required after the penalty is paid,
- whether the amount makes sense in relation to the secured obligation,
- whether a special protective legal regime applies.
Most importantly:
A higher contractual penalty is not automatically a better contractual penalty.
If the aim is genuinely to encourage performance, the amount should have commercial logic.
Not merely look intimidating.
LAWYER’S RECOMMENDATION + CHECKLIST
For every contractual penalty clause, I recommend one simple test:
Can I explain in one sentence what specific risk this penalty protects and why this particular calculation mechanism was chosen?
If the answer is:
“Because contracts usually contain some kind of penalty,”
the clause is not ready.
Quick checklist
The secured obligation is precisely identified.
It is clear what constitutes its breach.
It is clear who must pay the contractual penalty.
The amount or exact calculation method is defined.
For percentage penalties, the calculation base is defined.
It is clear whether the penalty is one-off or recurring.
For time-based penalties, the start and end of accrual are clear.
It is clear what constitutes one “individual breach”.
Accumulation of multiple penalties is addressed.
The amount has been tested against a long-running breach.
A maximum cap has been considered where appropriate.
The amount reflects the importance of the protected interest.
The relationship with damages is addressed.
It is clear whether damages may be claimed in addition to the penalty.
The due date of the contractual penalty is defined.
The mechanism for making the claim has been considered.
It is clear that paying the penalty does not replace the original obligation where performance is still required.
It has been checked whether any special statutory restrictions apply to the specific contractual relationship.
FAQ
What is a contractual penalty under Czech law?
A contractual penalty is a mechanism used to reinforce contractual obligations.
The parties agree that if a particular duty is breached, the creditor becomes entitled to a predetermined amount or an amount calculated according to an agreed formula.
The creditor does not need to prove actual damage in order to claim it.
Does the contractual penalty clause have to be included in the main agreement?
Not necessarily.
It may be included directly in the main contract or agreed separately in a Contractual Penalty Agreement linked to a particular contractual obligation.
The important point is that the connection with the secured obligation is sufficiently clear.
Does a Contractual Penalty Agreement have to be in writing?
Czech law does not generally impose a special written-form requirement solely because a contractual penalty is being agreed.
However, the form of the main legal transaction, the parties’ own agreement or other statutory rules may affect the position.
In practice, I would not rely on an oral contractual penalty arrangement, because the exact content and scope of the sanction are often disputed later.
Do I have to prove damage in order to claim a contractual penalty?
No.
Under Czech law, entitlement to the contractual penalty is not conditional on proving that actual damage occurred.
Can I claim both the contractual penalty and damages?
Be careful with the default rule.
Unless the parties agree otherwise, Czech law generally excludes a damages claim for loss caused by breach of the same obligation that is secured by the contractual penalty.
The parties may contractually modify this rule.
Can a Czech court reduce a contractual penalty?
Yes.
At the debtor’s request, a court may reduce a contractual penalty if the claim is disproportionately high.
Current Czech Supreme Court case law emphasises the specific contractual interest protected by the penalty, the circumstances of the breach and the proportionality of the particular claim that arose.
Is there a statutory maximum contractual penalty?
There is no single universal percentage or amount applicable to all ordinary contractual relationships.
The amount must be assessed in the context of the particular obligation, contractual relationship and actual breach.
Certain special legal regimes may impose additional restrictions.
If the debtor pays the contractual penalty, do they still have to perform the original obligation?
Generally, yes.
Payment of the contractual penalty does not normally release the debtor from the obligation that was secured by the penalty.
WHERE GENERAL INFORMATION ENDS
A contractual penalty may look like a universal clause.
In reality, the correct drafting depends heavily on which obligation it is intended to secure.
I would approach a penalty for:
delay in delivering work
differently, because a time-based mechanism may make sense,
than a penalty for:
breach of confidentiality,
where the key issue may be defining what constitutes one individual breach,
or a penalty for:
breach of exclusivity,
where the value of the protected commercial relationship may be crucial,
or a penalty for:
failure to return documentation or equipment,
where a combination of a one-off amount and continuing pressure to perform may be appropriate.
A contractual penalty is also not the same as other financial consequences of breach.
Contractual penalty vs. damages
With a contractual penalty, the creditor does not need to prove actual damage.
With a damages claim, the existence of loss and the other requirements for liability must be established.
Their relationship should also be addressed expressly.
Contractual penalty vs. default interest
Default interest typically responds to late payment of a monetary obligation.
A contractual penalty may be agreed for breach of many different types of contractual duties.
Whether the two mechanisms may operate together depends on the specific obligations and contractual structure.
Contractual penalty vs. termination
Termination or withdrawal deals with the continuation or end of the contractual relationship.
A contractual penalty deals with the financial consequence of breaching a particular obligation.
One does not automatically replace the other.
Contractual penalty vs. a lump-sum payment triggered by an event
Not every amount payable after a particular event is automatically a contractual penalty.
It is necessary to determine whether the payment is genuinely a sanction or reinforcement of a breached obligation, or instead represents a price, termination payment, settlement mechanism or another contractual payment arrangement.
This is where general information ends.
A specific contractual penalty cannot be properly designed without understanding:
- the main agreement,
- the specific obligation being secured,
- the commercial importance of that obligation,
- realistic breach scenarios,
- the possible duration of the breach,
- potential damage,
- the creditor’s other remedies,
- the termination mechanism,
- the bargaining position of the parties,
- any special legal regime that may apply.
First determine what the contractual penalty is supposed to protect. Only then decide what the breach should cost.
- Publikováno:
- Naposledy aktualizováno: 28/08/2026
Do you want to add a contractual penalty to an agreement and are unsure how to link it to the relevant obligations? I can review which obligations should be secured and how the penalty mechanism should work.
Get in touch and let’s schedule a meeting. I am a specialist on contract law – more information here. I also deal with Contractual Penalty Agreement on a daily basis (for more information see here).
Do you want to draft your own contract using AI?
You might be thinking about preparing your own contract – perhaps even with the help of artificial intelligence.
In some cases, that’s possible. But it’s essential to understand what to watch out for, how to structure your prompts correctly, and how to identify mistakes that AI commonly makes.
That’s why I’m preparing practical eBooks to guide you through the process step by step.
(The eBook page is currently in preparation – coming soon.)
You don’t have to wait.
If you plan to draft your contract using AI, it’s a good idea to have it reviewed by a lawyer first.
This helps you avoid mistakes that often only become apparent when it’s too late.
I can review your contract online – quickly and for a fixed fee.
How I help: Online lawyer | Online legal services | Online legal help | Online legal consultation| Prague online lawyer | Legal advice online |
Where I help: Lawyer Prague | Lawyer Prague 1 | Lawyer Prague 2 | Lawyer Prague 3 | Lawyer Prague 4 | Lawyer Prague 5 | Lawyer Prague 6 | Lawyer Prague 7 | Lawyer Prague 8 | Lawyer Prague 9 | Lawyer Prague 10 | Lawyer Brno | Lawyer Ostrava | Lawyer Pilsen | Lawyer Liberec | Lawyer Olomouc | Lawyer Hradec Králové | Lawyer České Budějovice | Lawyer Pardubice | Lawyer Zlín | Lawyer Ústí nad Labem
What I can help you with: Donation agreement | Purchase agreement | Loan for Use Agreement |
What else I can do: Contract lawyer | Debt collection lawyer | Enforcement & insolvency lawyer | Tax lawyer | Business lawyer | Corporate lawyer | Lawyer for HOAs and housing cooperatives